Worked example: moving in on 1 September 2027 near Sydney, a whole fit-out.

Building in
What you're ordering

Start with kitchen cabinetry: choose by 22 February 2027 and pay the deposit by 5 April 2027 to move in on 1 September 2027.

First decision22 February 2027127 days from today
Arrives in port21 July 2027Sydney
Move-in1 September 2027
  • Samples & specification
  • Production
  • Inspection
  • Loading
  • At sea
  • Customs & delivery
  • Installation time

Your dates

CategoryChoose byDeposit byStatus
Kitchen cabinetry22 Feb 20275 Apr 2027On track
Wardrobes & walk-in closets22 Feb 20275 Apr 2027On track
Dining tables & wooden chairs8 Mar 202719 Apr 2027On track
Wooden bedroom furniture15 Mar 202719 Apr 2027On track
Sofas & upholstered seating22 Mar 202726 Apr 2027On track
Lighting5 Apr 20273 May 2027On track
Marble & natural stone5 Apr 20273 May 2027On track
Porcelain & ceramic tiles19 Apr 202710 May 2027On track

What each step involves

  • Samples, drawings and specification sign-off: 22 February 2027 to 5 April 2027 (4–6 weeks for made-to-order pieces)
  • Production: 5 April 2027 to 14 June 2027 (7–10 weeks for kitchen cabinetry)
  • Final inspection and any fixes: 14 June 2027 to 21 June 2027
  • Booking, packing and loading the container: 21 June 2027 to 1 July 2027
  • Sea crossing to Sydney: 1 July 2027 to 21 July 2027 (Usually 16–20 days port to port)
  • Customs clearance and port release: 21 July 2027 to 28 July 2027
  • Delivery from the port to your home: 28 July 2027 to 4 August 2027
  • Installation and finishing time before move-in: 4 August 2027 to 1 September 2027
Factory closures we plan around. Chinese New Year 2027: 27 January 2027 to 21 February 2027 (New Year's Day is 6 February 2027; most factories stop for 2–4 weeks)
Golden Week 2027: 1 October 2027 to 7 October 2027 (National Day holiday)
Chinese New Year 2028: 16 January 2028 to 10 February 2028 (New Year's Day is 26 January 2028)

Get reminders before each date. We'll email you 30 days and 7 days before each decision and deposit date, and warn you before Chinese New Year.

Get your free sourcing plan

Send us your list and we'll come back with factory prices from Foshan, the containers and an honest view on what to buy locally. Free, and your first reply comes from Vinay.

Keep it

Everything you work out in these tools adds up in one project: your budget, containers, dates and trip. Save it to get a link by email, or print it.

How we work it out

For each category we start at your move-in date and work back, using the slow end of every range so the plan survives bad luck: your installation time, delivery from the port (1 week), customs and port release (1 week), the sea crossing to your port, booking and loading (10 days), the final inspection (1 week), production for that category (for example 7–10 weeks for kitchens and wardrobes, 5–7 for sofas, 3–5 for tiles) and, for made-to-order pieces, samples, drawings and sign-off (3–6 weeks).

If production or loading crosses Chinese New Year or Golden Week, the whole closure is added: factories wind down about ten days before New Year and take about two weeks after it to return to full speed.

Sources

Rates and rules last checked 15 October 2026.

Questions

How long does furniture from China take?

For made-to-order pieces, plan on 4–6 months from first sample to delivery to a US or Australian home: 3–6 weeks for samples and sign-off, 5–10 weeks of production, a week of inspection and loading, 2–5 weeks at sea and about two weeks for customs and delivery.

When is Chinese New Year 2027, and how does it affect orders?

New Year's Day is 6 February 2027. Most factories stop from late January until about 20 February, and workers return gradually. Orders confirmed in January often don't start production until March.

Can I get reminders?

Yes. Save your project and we'll email you 30 days and 7 days before each date.